UKDC has been involved in numerous cases which have helped to shape the law in many jurisdictions.

Search filters
01/05/2016
The demise of the OW Bunker group of companies in November, 2014, provoked litigation worldwide. In this industry leading case the Club supported the owner of the RES COGITANS in its efforts to avoid having to pay twice for fuel supplied to the ship. This culminated in a decision by the Supreme Court of England & Wales in favour of the bunker supplier.

11/09/2015
The Member entered in to shipbuilding contracts with a yard and paid several instalments of the contract price. The yard had established bank refund guarantees in respect of those payments, in the event the Member was entitled to rescind, cancel or terminate the contract. Neither the contract nor the guarantees envisaged the yard entering in to statutory insolvency protection and, when this occurred, the Member sought payment under the guarantees.  The bank resisted the Member’s demands, arguing on strict interpretation that insolvency was not specified as an event that triggered liability under the guarantees...

01/01/2015
An owner Member ordered a series of  ten ships from a Chinese shipyard in 2007. As building of the ships progressed, several issues arose with the quality of construction. A number of disputes arose, most of which were settled with some contracts being cancelled and others amended with delayed delivery dates. Construction for one of the hulls continued but that ship suffered a main engine breakdown during its pre-delivery sea trials. Disputes arose and the Member was eventually successful in recovering the repayment of $19.6m pre-instalments following a two part arbitration hearing.

01/01/2015
An owner Member pursued a claim for approximately $1.3 million for the consequence of improper remedial work to a ship’s main engine. ICC arbitration was brought against the engine maintenance technicians, which ultimately settled in the Member’s favour by means of commercial benefits including waiver of fees and extended engine warranties. 

01/01/2014
In this case the sub-charterer of the ship argued that the requirement for a disponent owner to seek permission from a head owner to transit the Gulf of Aden evinced an intention not to perform its obligations under the relevant charter...

01/01/2012
Following a major collision in 2009 the Member declared the ship to be a constructive total loss (“CTL”) and terminated its charter with Bunge. Bunge disputed that the ship was a CTL and challenged the Member’s termination of the charter. The Member brought a claim in London arbitration proceedings for a declaration that the charter was frustrated and Bunge counter-claimed for damages of over $9 million...

27/06/2010
The English High Court has today ruled (“The SALDANHA” – [2010] EWHC 1340 Comm) that a ship which was seized by pirates early in 2009 remained on-hire for the period of the detention. The case was brought by a Member entered in the Association.

01/01/2010
The English High Court considered whether the NYPE off-hire clause applied when a ship was detained by pirates. The charterer had placed the ship off hire for the duration of the detention, but failed to persuade the court that the piracy and hostage event should fall within the off-hire clause.  The court pointed out that parties should expressly provide for seizure events if they wished their rights to be certain...

01/01/2010
The Court of Appeal considered the owner’s claim for demurrage under an amended Shellvoy 5 charter with Shell additional clauses. A dispute arose because the ship was not granted free pratique within 6 hours of issuing notice of readiness. Although a second notice of readiness was given when the ship was granted free pratique, when the owner submitted its demurrage claim it did not include the second notice of readiness in the supporting documents. The court held that the owner’s claim was time barred and made clear the importance of fully complying with time limit provisions in a charter...

01/01/2009
Following loading at Yokohama the charterer instructed the ship to proceed to Shanghai. Meanwhile the ship sustained damage after colliding with a breakwater in and proceeded to Hong Kong to discharge all of her cargo and then to a repair yard in China. The owner accepted that the ship was off-hire during the delay following the incident however the initial routes from Yokohama to Hong Kong and Shanghai were identical and the owner claimed that the ship came back on hire for a period following departure from Japan. The London arbitration tribunal found in favour of the charterer however the award was overturned on appeal to the English High Court.  The court concluded that the important question was not what the ship was doing at a particular moment but what instructions she was operating under. Proceeding in the general direction of a port was not the same as proceeding to the designated port and the ship was off-hire as a result...

You are currently offline. Some pages or content may fail to load.